GTR delays and reliability
Great Northern, Thameslink, Southern and Gatwick Express (GTR)
How this operator is doing
GTR had 14,003,574 scheduled station stops across 329 stations in the 13 four-week periods to Period 7 of 2026-27. 82.9% of the stops with a recorded arrival came within three minutes of the timetable, and 4.7% of scheduled stops were cancelled.
The oldest stations GTR calls at are Deptford (1836), London Bridge (1836) and Harrow and Wealdstone (1837), and the newest are Brent Cross West (2023), Cambridge North (2017) and Imperial Wharf (2009).
GTR's northernmost stations are Kings Lynn and Watlington and its southernmost are Eastbourne and Seaford (Sussex).
The most isolated stations on the GTR network are Huntingdon (11.4 km from St Neots), St Neots (11.4 km from Huntingdon) and Peterborough (9.4 km from Whittlesea).
Experience varies widely across the 307 ranked stations of GTR. The best-served tenth reach 91.7% or more, the median is 83.8% and the worst tenth manage 72.5% or less, a spread of 19.2 percentage points. 180 stations fall below 85%.
For GTR, the weakest four-week period in the data is a recent one: Period 6 of 2026-27, when only 74.5% of stops arrived within three minutes of the timetable. The strongest was Period 1 of 2023-24, at 89.1%, which is 14.6 percentage points higher.
Delay Repay
GTR pays Delay Repay for a delay of 15 minutes or more, starting at 25% of a single ticket. The page sets the rules beside how often its trains run late. Read the GTR Delay Repay rules
Period by period
Least punctual stations
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Watlington | 17,138 | 62.7% | 10.0% |
| Downham Market | 17,149 | 64.2% | 10.0% |
| Kings Lynn | 17,260 | 65.1% | 9.8% |
| Littleport | 17,147 | 65.2% | 9.9% |
| Cooksbridge | 12,211 | 66.1% | 3.5% |
| Foxton | 18,869 | 66.8% | 5.1% |
Most punctual stations
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Beckenham Junction | 19,873 | 98.1% | 3.1% |
| Birkbeck | 19,535 | 98.1% | 2.8% |
| East Dulwich | 46,138 | 96.0% | 2.6% |
| Gipsy Hill | 65,513 | 95.4% | 2.8% |
| North Dulwich | 46,138 | 95.2% | 2.6% |
| West Norwood | 65,511 | 95.1% | 2.8% |
Busiest stations
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| East Croydon | 295,918 | 77.5% | 3.7% |
| London Victoria | 251,969 | 83.0% | 3.1% |
| London Bridge | 251,437 | 83.8% | 3.9% |
| Clapham Junction | 238,078 | 84.2% | 2.8% |
| Gatwick Airport | 202,328 | 71.2% | 4.7% |
| London Blackfriars | 199,652 | 80.4% | 5.4% |
Where it runs
| Area | Share of stops | Within 3 min | Cancelled |
|---|---|---|---|
| London | 49% | 86.0% | 4.5% |
| South East | 37% | 80.2% | 4.3% |
| East of England | 14% | 78.8% | 6.3% |
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 1,088,922 | 78.2% | 4.5% |
| Period 6 of 2026-27 | 1,054,030 | 74.5% | 6.0% |
| Period 5 of 2026-27 | 1,054,676 | 79.0% | 6.3% |
| Period 4 of 2026-27 | 1,090,214 | 82.0% | 5.2% |
| Period 3 of 2026-27 | 1,024,998 | 83.2% | 5.0% |
| Period 2 of 2026-27 | 1,051,738 | 85.6% | 4.8% |
| Period 1 of 2026-27 | 1,226,607 | 87.6% | 3.6% |
| Period 13 of 2025-26 | 1,190,661 | 87.6% | 3.2% |
| Period 12 of 2025-26 | 1,066,393 | 85.4% | 3.8% |
| Period 11 of 2025-26 | 1,058,642 | 84.2% | 3.9% |
| Period 10 of 2025-26 | 937,638 | 84.8% | 4.6% |
| Period 9 of 2025-26 | 1,081,465 | 80.6% | 6.0% |
| Period 8 of 2025-26 | 1,077,590 | 83.2% | 4.3% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out