LNER at Doncaster
All trains at DoncasterLNER across BritainYorkshire and The Humber
How this operator is doing here
LNER had 42,065 scheduled stops at Doncaster in the 13 periods to Period 7 of 2026-27, 32% of the station's total. 66.0% of recorded arrivals came within three minutes and 2.8% of stops were cancelled.
LNER trains at Doncaster also serve Retford (26.5 km south-east, 72.6% on time, 3.5% cancelled), Selby (29.5 km north, 71.9% on time, 7.3% cancelled), Wakefield Westgate (30.0 km north-west, 64.7% on time, 3.7% cancelled), Leeds (40.5 km north-west, 70.1% on time, 3.8% cancelled), Brough (43.5 km north-east, 69.0% on time, 5.6% cancelled) and Horsforth (48.5 km north-west, 73.1% on time, 6.2% cancelled), which are the stations on its network closest to Doncaster.
The busiest LNER station within 30 km of Doncaster is Wakefield Westgate, 30.0 km north-west, with about 62 scheduled stops a day.
LNER ranks 4th of the 7 operators with enough records at Doncaster, on 66.0%.
For LNER, Doncaster is the 17th best of 35 ranked stations. Its 66.0% here is 1.6 percentage points below the 67.6% across the whole network.
LNER at Doncaster has slipped a little, from 70.6% within three minutes in the previous 13 periods to 66.0% in the latest 13, a fall of 4.6 percentage points. Cancellations rose to 2.8% of scheduled stops from 2.0%, which is 0.8 percentage points more.
Period by period
See how LNER Delay Repay works
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 3,278 | 67.5% | 1.4% |
| Period 6 of 2026-27 | 3,302 | 61.5% | 3.3% |
| Period 5 of 2026-27 | 3,340 | 61.3% | 4.2% |
| Period 4 of 2026-27 | 3,350 | 63.3% | 2.4% |
| Period 3 of 2026-27 | 3,211 | 61.2% | 2.1% |
| Period 2 of 2026-27 | 3,307 | 64.3% | 3.5% |
| Period 1 of 2026-27 | 3,835 | 65.9% | 4.4% |
| Period 13 of 2025-26 | 3,515 | 71.5% | 2.2% |
| Period 12 of 2025-26 | 3,009 | 69.5% | 2.5% |
| Period 11 of 2025-26 | 3,107 | 68.5% | 3.0% |
| Period 10 of 2025-26 | 2,878 | 66.8% | 1.7% |
| Period 9 of 2025-26 | 2,932 | 65.8% | 4.2% |
| Period 8 of 2025-26 | 3,001 | 71.9% | 1.7% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Other operators at Doncaster
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Northern | 58,027 | 83.2% | 2.8% |
| TransPennine Express | 12,769 | 67.9% | 2.5% |
| CrossCountry | 6,797 | 57.1% | 5.7% |
| Hull Trains | 4,857 | 64.4% | 0.6% |
| East Midlands Railway | 3,154 | 88.6% | 2.5% |
| Grand Central | 2,849 | 51.5% | 2.2% |
| Lumo (East Coast) | 4 | – | – |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out