Avanti at Motherwell
How this operator is doing here
Avanti had 7,258 scheduled stops at Motherwell in the 13 periods to Period 7 of 2026-27, 9% of the station's total. 57.9% of recorded arrivals came within three minutes and 5.4% of stops were cancelled.
Avanti trains at Motherwell also serve Shieldmuir (2.8 km south-east, – on time, – cancelled), Glasgow Central (18.0 km north-west, 64.7% on time, 5.5% cancelled), Haymarket (51.3 km east, 66.1% on time, 4.5% cancelled), Edinburgh (53.3 km east, 66.3% on time, 4.4% cancelled), Lockerbie (84.7 km south-east, 53.1% on time, 5.0% cancelled) and Carlisle (120.7 km south-east, 51.7% on time, 4.6% cancelled), which are the stations on its network closest to Motherwell.
The busiest Avanti station within 30 km of Motherwell is Glasgow Central, 18.0 km north-west, with about 38 scheduled stops a day.
Of the 5 operators with enough records at Motherwell, Avanti is the least punctual, at 57.9%.
Avanti at Motherwell has slipped a little, from 61.7% within three minutes in the previous 13 periods to 57.9% in the latest 13, a fall of 3.8 percentage points. Cancellations rose to 5.4% of scheduled stops from 4.9%, which is 0.5 percentage points more.
Avanti at Motherwell has not moved in one direction over three full railway years: 64.5% within three minutes in 2023-24, 66.1% in 2024-25 and 59.6% in 2025-26.
Period by period
See how Avanti Delay Repay works
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 592 | 58.5% | 2.2% |
| Period 6 of 2026-27 | 584 | 51.8% | 0.9% |
| Period 5 of 2026-27 | 593 | 53.4% | 5.9% |
| Period 4 of 2026-27 | 592 | 51.7% | 8.8% |
| Period 3 of 2026-27 | 561 | 62.8% | 3.6% |
| Period 2 of 2026-27 | 468 | 59.4% | 3.6% |
| Period 1 of 2026-27 | 350 | 59.7% | 1.4% |
| Period 13 of 2025-26 | 760 | 57.0% | 8.6% |
| Period 12 of 2025-26 | 588 | 66.2% | 5.3% |
| Period 11 of 2025-26 | 524 | 74.0% | 2.5% |
| Period 10 of 2025-26 | 507 | 57.1% | 7.7% |
| Period 9 of 2025-26 | 588 | 47.2% | 10.2% |
| Period 8 of 2025-26 | 551 | 56.3% | 6.9% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Other operators at Motherwell
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| ScotRail | 69,206 | 83.7% | 1.6% |
| TransPennine Express | 5,587 | 67.7% | 6.3% |
| CrossCountry | 1,600 | 74.4% | 8.2% |
| Lumo (West Coast) | 721 | 62.1% | 5.1% |
| Caledonian Sleeper | 588 | – | – |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out