GTR had 22,343 scheduled stops at Slade Green in the 13 periods to Period 7 of 2026-27, 28% of the station's total. 84.9% of recorded arrivals came within three minutes and 6.4% of stops were cancelled.
GTR trains at Slade Green also serve Barnehurst (2.1 km west, 88.7% on time, 1.3% cancelled), Dartford (3.0 km south-east, 78.2% on time, 5.0% cancelled), Bexleyheath (4.0 km west, 90.0% on time, 1.3% cancelled), Stone Crossing (5.4 km east, 82.6% on time, 5.1% cancelled), Abbey Wood (5.5 km north-west, 86.0% on time, 6.4% cancelled) and Greenhithe for Bluewater (6.5 km east, 83.4% on time, 5.1% cancelled), which are the stations on its network closest to Slade Green.
Within 30 km of here, GTR runs best at Beckenham Junction, 16.3 km south-west (98.1%), and worst at Kenley, 25.7 km south-west (66.9%).
The busiest GTR station within 30 km of Slade Green is East Croydon, 22.2 km south-west, with about 813 scheduled stops a day.
Of the 2 operators with enough records at Slade Green, GTR is the least punctual, at 84.9%.
For GTR, Slade Green is the 129th best of 307 ranked stations. Its 84.9% here is 2.0 percentage points above the 82.9% across the whole network.
Period by period
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 1,925 | 85.3% | 5.5% |
| Period 6 of 2026-27 | 1,748 | 81.6% | 4.9% |
| Period 5 of 2026-27 | 1,363 | 84.5% | 6.9% |
| Period 4 of 2026-27 | 1,744 | 83.8% | 4.0% |
| Period 3 of 2026-27 | 1,257 | 82.7% | 6.0% |
| Period 2 of 2026-27 | 1,878 | 84.4% | 5.3% |
| Period 1 of 2026-27 | 1,993 | 87.7% | 4.7% |
| Period 13 of 2025-26 | 2,067 | 87.4% | 2.8% |
| Period 12 of 2025-26 | 1,185 | 83.9% | 10.2% |
| Period 11 of 2025-26 | 1,797 | 86.6% | 8.8% |
| Period 10 of 2025-26 | 1,789 | 89.0% | 8.8% |
| Period 9 of 2025-26 | 1,809 | 82.5% | 10.6% |
| Period 8 of 2025-26 | 1,788 | 82.0% | 7.2% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Other operators at Slade Green
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Southeastern | 57,183 | 90.8% | 1.6% |