How this operator is doing here
East Midlands Railway had 35,468 scheduled stops at Chesterfield in the 13 periods to Period 7 of 2026-27, 59% of the station's total. 61.3% of recorded arrivals came within three minutes and 4.3% of stops were cancelled.
East Midlands Railway trains at Chesterfield also serve Dronfield (7.7 km north-west, 65.2% on time, 3.2% cancelled), Dore and Totley (11.8 km north-west, 45.9% on time, 3.8% cancelled), Creswell (13.9 km east, – on time, 3.6% cancelled), Langwith-Whaley Thorns (14.1 km east, – on time, 3.7% cancelled), Matlock (14.5 km south-west, 85.4% on time, 2.6% cancelled) and Shirebrook (15.0 km east, – on time, 3.5% cancelled), which are the stations on its network closest to Chesterfield.
Within 30 km of here, East Midlands Railway runs best at Newstead, 22.9 km south-east (88.2%), and worst at Sheffield, 15.8 km north (57.7%).
The busiest East Midlands Railway station within 30 km of Chesterfield is Sheffield, 15.8 km north, with about 97 scheduled stops a day.
East Midlands Railway at Chesterfield has slipped sharply. 61.3% of stops came within three minutes of the timetable in the latest 13 periods, 5.9 percentage points worse than the 67.2% recorded in the 13 before. Cancellations rose to 4.3% of scheduled stops from 2.9%, which is 1.4 percentage points more.
Period by period
See how East Midlands Railway Delay Repay works
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 2,690 | 62.5% | 3.1% |
| Period 6 of 2026-27 | 2,579 | 58.0% | 3.1% |
| Period 5 of 2026-27 | 2,407 | 58.8% | 5.5% |
| Period 4 of 2026-27 | 2,580 | 58.7% | 7.6% |
| Period 3 of 2026-27 | 2,471 | 53.1% | 7.5% |
| Period 2 of 2026-27 | 2,776 | 58.2% | 5.4% |
| Period 1 of 2026-27 | 3,191 | 63.2% | 3.6% |
| Period 13 of 2025-26 | 3,061 | 59.9% | 4.8% |
| Period 12 of 2025-26 | 2,824 | 65.9% | 3.7% |
| Period 11 of 2025-26 | 2,801 | 70.1% | 3.8% |
| Period 10 of 2025-26 | 2,530 | 66.0% | 3.2% |
| Period 9 of 2025-26 | 2,762 | 57.9% | 3.2% |
| Period 8 of 2025-26 | 2,796 | 62.2% | 1.6% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Other operators at Chesterfield
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Northern | 12,853 | 79.1% | 1.9% |
| CrossCountry | 11,982 | 54.2% | 2.6% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out