Elizabeth line at Abbey Wood
How this operator is doing here
Elizabeth line had 113,999 scheduled stops at Abbey Wood in the 13 periods to Period 7 of 2026-27, 59% of the station's total. 94.9% of recorded arrivals came within three minutes and 2.5% of stops were cancelled.
Elizabeth line trains at Abbey Wood also serve Woolwich (3.4 km west, 93.9% on time, 2.5% cancelled), Custom House (6.8 km west, 93.8% on time, 2.5% cancelled), Seven Kings (8.3 km north, 88.3% on time, 2.5% cancelled), Goodmayes (8.3 km north, 88.6% on time, 2.5% cancelled), Ilford (8.4 km north-west, 90.1% on time, 2.2% cancelled) and Manor Park (8.6 km north-west, 89.5% on time, 2.5% cancelled), which are the stations on its network closest to Abbey Wood.
Within 30 km of here, Elizabeth line runs best at Woolwich, 3.4 km west (93.9%), and worst at Ealing Broadway, 29.3 km west (82.9%).
The busiest Elizabeth line station within 30 km of Abbey Wood is London Paddington, 20.8 km west, with about 644 scheduled stops a day.
Of the 3 operators with enough records at Abbey Wood, Elizabeth line is the most punctual, at 94.9%.
Abbey Wood is the most punctual station on the Elizabeth line network, out of 41 ranked stations: 94.9% here against 89.6% across the whole network, which is 5.3 percentage points better.
Period by period
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 8,776 | 95.2% | 2.1% |
| Period 6 of 2026-27 | 8,744 | 94.8% | 3.4% |
| Period 5 of 2026-27 | 8,776 | 92.9% | 4.4% |
| Period 4 of 2026-27 | 8,795 | 94.2% | 1.3% |
| Period 3 of 2026-27 | 8,497 | 93.1% | 1.9% |
| Period 2 of 2026-27 | 8,688 | 95.2% | 3.0% |
| Period 1 of 2026-27 | 10,000 | 95.5% | 2.9% |
| Period 13 of 2025-26 | 9,542 | 94.8% | 1.2% |
| Period 12 of 2025-26 | 8,690 | 96.0% | 0.9% |
| Period 11 of 2025-26 | 8,776 | 95.2% | 3.6% |
| Period 10 of 2025-26 | 7,845 | 97.0% | 1.9% |
| Period 9 of 2025-26 | 8,238 | 94.4% | 2.2% |
| Period 8 of 2025-26 | 8,632 | 95.2% | 4.3% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Other operators at Abbey Wood
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Southeastern | 56,258 | 92.0% | 1.6% |
| GTR | 22,343 | 86.0% | 6.4% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out