Winchfield
WNFSouth EastManaged by South Western Railway
How this station is performing
Winchfield had 22,959 scheduled stops to Period 7 of 2026-27, about 63 a day. 86.1% of recorded arrivals were within three minutes of the timetable and 2.5% of scheduled stops were cancelled.
Winchfield opened on 24 September 1838, 188 years before the latest figures here, and has not been moved since. Of the 5 stations nearest to it with a known opening date, Winchfield is the oldest; the next oldest, Farnborough (Main), dates from 1838.
The nearest stations to Winchfield are Hook (3.8 km west), Fleet (5.3 km east), Sandhurst (Berks) (10.0 km north-east), Blackwater (10.5 km north-east) and Farnborough (Main) (10.6 km east). 3 stations lie within 10 km in all. Of the five, Hook is the most punctual at 87.8% and Fleet the least at 79.6%, with Winchfield on 86.1%.
Winchfield takes its name from a Village called Winchfield, home to about 713 people, and the station stands 1.9 km from its centre.
Across the whole run of data, the weakest four-week period for Winchfield was Period 9 of 2023-24, at 71.4%, some time before the latest year. The strongest was Period 5 of 2023-24, at 94.3%, and the two are 22.9 percentage points apart. Cancellations peaked at 9.8% of scheduled stops in Period 1 of 2024-25, against 2.5% over the latest 13 periods.
Compared with 3 stations of a similar size in South East, Winchfield is the most punctual, at 86.1%. The comparison group includes Arundel (77.3%), Billingshurst (74.5%) and Pulborough (75.1%).
Period by period
Operators calling here
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| South Western Railway | 22,959 | 86.1% | 2.5% |
Operators with their own page for this station are linked to it.
Late train at Winchfield? Delay Repay
These operators call at Winchfield and publish Delay Repay rules.
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 1,696 | 82.4% | 2.9% |
| Period 6 of 2026-27 | 1,800 | 87.8% | 0.9% |
| Period 5 of 2026-27 | 1,796 | 87.0% | 3.4% |
| Period 4 of 2026-27 | 1,801 | 87.5% | 2.7% |
| Period 3 of 2026-27 | 1,699 | 89.8% | 2.5% |
| Period 2 of 2026-27 | 1,693 | 81.3% | 6.3% |
| Period 1 of 2026-27 | 1,981 | 91.5% | 2.0% |
| Period 13 of 2025-26 | 1,937 | 92.3% | 1.1% |
| Period 12 of 2025-26 | 1,796 | 89.5% | 2.0% |
| Period 11 of 2025-26 | 1,731 | 89.0% | 0.8% |
| Period 10 of 2025-26 | 1,545 | 84.8% | 2.8% |
| Period 9 of 2025-26 | 1,689 | 73.5% | 2.8% |
| Period 8 of 2025-26 | 1,795 | 80.2% | 2.5% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Similar stations in South East
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Arundel | 22,988 | 77.3% | 2.8% |
| Billingshurst | 22,988 | 74.5% | 2.8% |
| Pulborough | 22,989 | 75.1% | 2.7% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out