Billingshurst
BIGSouth EastManaged by Govia Thameslink Railway (Southern)
How this station is performing
Billingshurst had 22,988 scheduled stops to Period 7 of 2026-27, about 63 a day. 74.5% of recorded arrivals were within three minutes of the timetable and 2.8% of scheduled stops were cancelled.
Billingshurst opened on 10 October 1859, 167 years before the latest figures here, and has not been moved since. Among the 5 stations nearest to it with a known opening date, Horsham is the oldest (1848) and Littlehaven the newest (1907), with Billingshurst in between.
The nearest stations to Billingshurst are Christs Hospital (7.2 km north-east), Pulborough (7.9 km south-west), Horsham (10.8 km north-east), Warnham (12.1 km north-east) and Littlehaven (12.2 km north-east). 2 stations lie within 10 km in all. Of the five, Littlehaven is the most punctual at 79.1% and Horsham the least at 72.6%, with Billingshurst on 74.5%.
Billingshurst takes its name from a Village called Billingshurst, home to about 8,232 people, and the station stands 0.8 km from its centre.
For Billingshurst, the weakest four-week period in the data is a recent one: Period 6 of 2026-27, when only 32.0% of stops arrived within three minutes of the timetable. The strongest was Period 1 of 2023-24, at 89.4%, which is 57.4 percentage points higher. Cancellations peaked at 7.4% of scheduled stops in Period 5 of 2026-27, against 2.8% over the latest 13 periods.
Compared with 3 stations of a similar size in South East, Billingshurst is the least punctual, at 74.5%. All of them are ahead, including Arundel (77.3%), Pulborough (75.1%) and Winchfield (86.1%).
Period by period
Operators calling here
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| GTR | 22,988 | 74.5% | 2.8% |
Operators with their own page for this station are linked to it.
Late train at Billingshurst? Delay Repay
These operators call at Billingshurst and publish Delay Repay rules.
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 1,754 | 69.3% | 2.5% |
| Period 6 of 2026-27 | 1,282 | 32.0% | 2.9% |
| Period 5 of 2026-27 | 1,778 | 62.4% | 7.4% |
| Period 4 of 2026-27 | 1,806 | 73.6% | 2.8% |
| Period 3 of 2026-27 | 1,789 | 77.0% | 3.7% |
| Period 2 of 2026-27 | 1,802 | 79.1% | 2.5% |
| Period 1 of 2026-27 | 2,076 | 83.5% | 1.7% |
| Period 13 of 2025-26 | 1,965 | 85.1% | 2.0% |
| Period 12 of 2025-26 | 1,772 | 81.6% | 1.6% |
| Period 11 of 2025-26 | 1,816 | 79.7% | 2.8% |
| Period 10 of 2025-26 | 1,565 | 77.6% | 1.9% |
| Period 9 of 2025-26 | 1,810 | 73.3% | 1.9% |
| Period 8 of 2025-26 | 1,773 | 79.6% | 2.6% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Similar stations in South East
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Arundel | 22,988 | 77.3% | 2.8% |
| Pulborough | 22,989 | 75.1% | 2.7% |
| Winchfield | 22,959 | 86.1% | 2.5% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out