Salford Crescent
SLDNorth WestManaged by Northern Trains
How this station is performing
Salford Crescent had 88,724 scheduled stops to Period 7 of 2026-27, about 244 a day. 74.3% of recorded arrivals were within three minutes of the timetable and 3.4% of scheduled stops were cancelled.
Salford Crescent opened on 11 May 1987, 39 years before the latest figures here, and has not been moved since. Of the 5 stations nearest to it with a known opening date, Salford Crescent is the newest; the oldest, Salford Central, opened in 1838.
The nearest stations to Salford Crescent are Salford Central (1.4 km east), Deansgate (2.1 km south-east), Manchester Victoria (2.2 km east), Manchester Oxford Road (2.6 km south-east) and Manchester Piccadilly (3.2 km east). 32 stations lie within 10 km in all. Of the five, Salford Central is the most punctual at 78.5% and Manchester Oxford Road the least at 55.5%, with Salford Crescent on 74.3%.
Salford Crescent is named after Salford, a big city, home to about 103,886 people, but the station stands 1.2 km from its centre.
For Salford Crescent, the weakest four-week period in the data is a recent one: Period 9 of 2025-26, when only 62.7% of stops arrived within three minutes of the timetable. The strongest was Period 1 of 2023-24, at 89.4%, which is 26.7 percentage points higher. Cancellations peaked at 9.6% of scheduled stops in Period 10 of 2024-25, against 3.4% over the latest 13 periods.
1 of 3 stations of a similar size in North West are more punctual than Salford Crescent on 74.3%. The comparison group includes Kirkdale (91.2%), Bolton (60.6%) and Manchester Airport (72.4%).
Period by period
Operators calling here
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Northern | 88,723 | 74.3% | 3.4% |
| TransPennine Express | 1 | – | – |
Operators with their own page for this station are linked to it.
Late train at Salford Crescent? Delay Repay
These operators call at Salford Crescent and publish Delay Repay rules.
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 6,815 | 71.9% | 2.7% |
| Period 6 of 2026-27 | 6,806 | 77.0% | 2.2% |
| Period 5 of 2026-27 | 6,774 | 77.4% | 4.9% |
| Period 4 of 2026-27 | 6,479 | 73.2% | 4.2% |
| Period 3 of 2026-27 | 6,222 | 74.7% | 3.7% |
| Period 2 of 2026-27 | 6,816 | 74.0% | 3.2% |
| Period 1 of 2026-27 | 7,904 | 77.0% | 2.2% |
| Period 13 of 2025-26 | 7,436 | 77.7% | 4.3% |
| Period 12 of 2025-26 | 6,855 | 77.8% | 2.2% |
| Period 11 of 2025-26 | 6,799 | 76.0% | 2.4% |
| Period 10 of 2025-26 | 6,204 | 74.5% | 5.6% |
| Period 9 of 2025-26 | 6,812 | 62.7% | 4.3% |
| Period 8 of 2025-26 | 6,802 | 71.0% | 3.3% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Similar stations in North West
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Kirkdale | 85,826 | 91.2% | 1.7% |
| Bolton | 84,707 | 60.6% | 3.7% |
| Manchester Airport | 93,105 | 72.4% | 5.7% |