Possilpark and Parkhouse
PPKScotlandManaged by ScotRail
How this station is performing
Possilpark and Parkhouse had 17,206 scheduled stops to Period 7 of 2026-27, about 47 a day. 93.5% of recorded arrivals were within three minutes of the timetable and 1.2% of scheduled stops were cancelled.
Possilpark and Parkhouse opened on 2 February 1885 and closed to passengers on 29 February 1964. It reopened on 3 December 1993, 33 years before the latest figures. Among the 5 stations nearest to it with a known opening date, Summerston is the oldest (1879) and Gilshochill the newest (1993), with Possilpark and Parkhouse in between.
The nearest stations to Possilpark and Parkhouse are Ashfield (0.6 km east), Gilshochill (1.7 km north-west), Springburn (2.0 km south-east), Summerston (2.3 km north-west) and Barnhill (2.6 km south-east). 72 stations lie within 10 km in all. Of the five, Summerston is the most punctual at 95.3% and Barnhill the least at 89.1%, with Possilpark and Parkhouse on 93.5%.
Possilpark and Parkhouse is named after Parkhouse, a neighborhood, but the station stands 0.5 km from its centre.
Across the whole run of data, the weakest four-week period for Possilpark and Parkhouse was Period 8 of 2024-25, at 84.0%, some time before the latest year. The strongest was Period 6 of 2024-25, at 97.9%, and the two are 13.9 percentage points apart.
Compared with 3 stations of a similar size in Scotland, Possilpark and Parkhouse is the least punctual, at 93.5%. All of them are ahead, including Maryhill (93.9%), Ashfield (94.2%) and Gilshochill (95.3%).
Period by period
Operators calling here
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| ScotRail | 17,206 | 93.5% | 1.2% |
Operators with their own page for this station are linked to it.
Late train at Possilpark and Parkhouse? Delay Repay
These operators call at Possilpark and Parkhouse and publish Delay Repay rules.
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 1,328 | 93.6% | 0.6% |
| Period 6 of 2026-27 | 1,328 | 95.5% | 0.5% |
| Period 5 of 2026-27 | 1,328 | 92.4% | 1.5% |
| Period 4 of 2026-27 | 1,328 | 93.6% | 1.9% |
| Period 3 of 2026-27 | 1,328 | 93.9% | 1.4% |
| Period 2 of 2026-27 | 1,316 | 94.3% | 1.1% |
| Period 1 of 2026-27 | 1,488 | 94.2% | 3.2% |
| Period 13 of 2025-26 | 1,426 | 95.4% | 1.1% |
| Period 12 of 2025-26 | 1,304 | 94.2% | 0.2% |
| Period 11 of 2025-26 | 1,304 | 92.3% | 0.9% |
| Period 10 of 2025-26 | 1,122 | 92.8% | 1.2% |
| Period 9 of 2025-26 | 1,303 | 89.9% | 1.8% |
| Period 8 of 2025-26 | 1,303 | 92.1% | 0.5% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Similar stations in Scotland
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Maryhill | 17,206 | 93.9% | 1.2% |
| Ashfield | 16,920 | 94.2% | 1.2% |
| Gilshochill | 16,920 | 95.3% | 1.3% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out