Southeastern at Peckham Rye
How this operator is doing here
Southeastern had 25,159 scheduled stops at Peckham Rye in the 13 periods to Period 7 of 2026-27, 16% of the station's total. 81.3% of recorded arrivals came within three minutes and 2.0% of stops were cancelled.
Southeastern trains at Peckham Rye also serve Nunhead (1.2 km east, 86.1% on time, 2.2% cancelled), Denmark Hill (1.4 km west, 83.8% on time, 2.3% cancelled), Loughborough Junction (2.3 km west, 90.2% on time, 2.2% cancelled), New Cross (2.6 km east, 90.1% on time, 1.5% cancelled), Crofton Park (2.8 km south-east, 83.4% on time, 2.8% cancelled) and Herne Hill (2.9 km south-west, 80.8% on time, 2.4% cancelled), which are the stations on its network closest to Peckham Rye.
Within 30 km of here, Southeastern runs best at Sundridge Park, 8.9 km south-east (99.4%), and worst at Sevenoaks, 27.7 km south-east (72.3%).
The busiest Southeastern station within 30 km of Peckham Rye is London Bridge, 4.0 km north, with about 912 scheduled stops a day.
Southeastern at Peckham Rye improved sharply over the past year. In the latest 13 periods 81.3% of stops came within three minutes of the timetable, up 5.4 percentage points from 75.9% in the 13 before. Cancellations held steady at 2.0% of scheduled stops, against 2.2% before.
Period by period
See how Southeastern Delay Repay works
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 1,825 | 80.7% | 1.8% |
| Period 6 of 2026-27 | 1,896 | 78.8% | 0.8% |
| Period 5 of 2026-27 | 2,051 | 74.8% | 2.8% |
| Period 4 of 2026-27 | 1,896 | 80.9% | 2.1% |
| Period 3 of 2026-27 | 1,963 | 78.3% | 1.9% |
| Period 2 of 2026-27 | 1,906 | 81.9% | 9.9% |
| Period 1 of 2026-27 | 2,327 | 89.4% | 1.2% |
| Period 13 of 2025-26 | 1,896 | 85.3% | 1.0% |
| Period 12 of 2025-26 | 1,981 | 86.4% | 0.9% |
| Period 11 of 2025-26 | 1,896 | 81.4% | 1.1% |
| Period 10 of 2025-26 | 1,510 | 77.4% | 2.2% |
| Period 9 of 2025-26 | 1,981 | 80.3% | 0.3% |
| Period 8 of 2025-26 | 2,031 | 78.7% | 0.8% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Other operators at Peckham Rye
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| GTR | 78,939 | 91.6% | 3.2% |
| London Overground | 49,636 | 90.3% | 4.5% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out