Hoxton
HOXLondonManaged by London Overground
How this station is performing
Hoxton had 209,634 scheduled stops to Period 7 of 2026-27, about 576 a day. 91.9% of recorded arrivals were within three minutes of the timetable and 3.9% of scheduled stops were cancelled.
Hoxton opened on 23 May 2010, 16 years before the latest figures here, and has not been moved since. Of the 5 stations nearest to it with a known opening date, Hoxton is the newest; the oldest, Haggerston, opened in 1867.
The nearest stations to Hoxton are Haggerston (0.8 km north), Shoreditch High Street (0.9 km south), Old Street (1.1 km south-west), Cambridge Heath (1.3 km east) and Bethnal Green (1.4 km south-east). 129 stations lie within 10 km in all. Of the five, Cambridge Heath is the most punctual at 93.2% and Old Street the least at 90.2%, with Hoxton on 91.9%.
Hoxton takes its name from an area of London called Hoxton, and the station stands 0.7 km from its centre.
Across the whole run of data, the weakest four-week period for Hoxton was Period 9 of 2023-24, at 87.2%, some time before the latest year. The strongest was Period 5 of 2024-25, at 96.7%, and the two are 9.5 percentage points apart. Cancellations peaked at 10.6% of scheduled stops in Period 5 of 2026-27, against 3.9% over the latest 13 periods.
1 of 3 stations of a similar size in London are more punctual than Hoxton on 91.9%. The comparison group includes Haggerston (91.4%), Rotherhithe (91.1%) and Shadwell (92.2%).
Period by period
Operators calling here
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| London Overground | 209,634 | 91.9% | 3.9% |
Operators with their own page for this station are linked to it.
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 16,192 | 89.4% | 2.8% |
| Period 6 of 2026-27 | 15,449 | 88.7% | 5.4% |
| Period 5 of 2026-27 | 15,600 | 90.5% | 10.6% |
| Period 4 of 2026-27 | 16,089 | 92.4% | 5.4% |
| Period 3 of 2026-27 | 16,340 | 92.4% | 3.0% |
| Period 2 of 2026-27 | 15,854 | 93.2% | 4.0% |
| Period 1 of 2026-27 | 18,739 | 93.0% | 3.5% |
| Period 13 of 2025-26 | 16,629 | 94.3% | 2.9% |
| Period 12 of 2025-26 | 16,120 | 94.0% | 3.0% |
| Period 11 of 2025-26 | 16,259 | 91.8% | 2.9% |
| Period 10 of 2025-26 | 14,481 | 93.4% | 2.0% |
| Period 9 of 2025-26 | 16,093 | 90.0% | 2.9% |
| Period 8 of 2025-26 | 15,789 | 91.3% | 2.7% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Similar stations in London
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Haggerston | 209,634 | 91.4% | 3.9% |
| Rotherhithe | 209,634 | 91.1% | 3.7% |
| Shadwell | 209,634 | 92.2% | 3.7% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out