GTR had 79,665 scheduled stops at Harpenden in the 13 periods to Period 7 of 2026-27, 100% of the station's total. 80.1% of recorded arrivals came within three minutes and 5.7% of stops were cancelled.
GTR trains at Harpenden also serve Luton Airport Parkway (7.1 km north-west, 79.5% on time, 5.1% cancelled), St Albans City (7.3 km south, 72.2% on time, 5.3% cancelled), Luton (8.7 km north-west, 82.8% on time, 5.1% cancelled), Welwyn Garden City (10.3 km east, 85.0% on time, 4.8% cancelled), Hatfield (Herts) (10.9 km south-east, 86.5% on time, 5.3% cancelled) and Welwyn North (11.0 km east, 72.5% on time, 5.8% cancelled), which are the stations on its network closest to Harpenden.
Within 30 km of here, GTR runs best at Cuffley, 20.4 km south-east (92.1%), and worst at Mill Hill Broadway, 23.6 km south (70.4%).
The busiest GTR station within 30 km of Harpenden is St Albans City, 7.3 km south, with about 329 scheduled stops a day.
Of the 1 operators with enough records at Harpenden, GTR is the most punctual, at 80.1%.
For GTR, Harpenden is the 205th best of 307 ranked stations. Its 80.1% here is 2.8 percentage points below the 82.9% across the whole network.
Period by period
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 6,412 | 78.2% | 3.9% |
| Period 6 of 2026-27 | 6,139 | 75.5% | 6.8% |
| Period 5 of 2026-27 | 5,614 | 75.3% | 8.3% |
| Period 4 of 2026-27 | 6,041 | 75.4% | 7.2% |
| Period 3 of 2026-27 | 4,569 | 81.5% | 3.5% |
| Period 2 of 2026-27 | 5,764 | 84.0% | 3.7% |
| Period 1 of 2026-27 | 6,944 | 85.5% | 3.4% |
| Period 13 of 2025-26 | 7,037 | 82.6% | 3.1% |
| Period 12 of 2025-26 | 6,355 | 84.1% | 6.9% |
| Period 11 of 2025-26 | 6,392 | 80.0% | 6.2% |
| Period 10 of 2025-26 | 5,654 | 83.2% | 6.6% |
| Period 9 of 2025-26 | 6,431 | 75.6% | 9.5% |
| Period 8 of 2025-26 | 6,313 | 79.2% | 4.8% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out