Croftfoot
CFFScotlandManaged by ScotRail
How this station is performing
Croftfoot had 24,244 scheduled stops to Period 7 of 2026-27, about 67 a day. 94.3% of recorded arrivals were within three minutes of the timetable and 1.4% of scheduled stops were cancelled.
Croftfoot opened on 1 April 1931, 95 years before the latest figures here, and has not been moved since. Of the 5 stations nearest to it with a known opening date, Croftfoot is the newest; the oldest, Rutherglen, opened in 1849.
The nearest stations to Croftfoot are Kings Park (1.1 km west), Burnside (South Lanarkshire) (1.6 km east), Rutherglen (1.7 km north-east), Cathcart (2.0 km west) and Mount Florida (2.3 km north-west). 75 stations lie within 10 km in all. Of the five, Mount Florida is the most punctual at 95.9% and Rutherglen the least at 83.5%, with Croftfoot on 94.3%.
In Scotland, Croftfoot ranks 41st of 313 ranked stations. Its 94.3% is 6.6 percentage points better than the area median of 87.7%.
Across the whole run of data, the weakest four-week period for Croftfoot was Period 8 of 2024-25, at 87.7%, some time before the latest year. The strongest was Period 2 of 2023-24, at 98.6%, and the two are 10.9 percentage points apart. Cancellations peaked at 5.5% of scheduled stops in Period 6 of 2024-25, against 1.4% over the latest 13 periods.
Compared with 3 stations of a similar size in Scotland, Croftfoot is the most punctual, at 94.3%. The comparison group includes Burnside (South Lanarkshire) (94.0%), Kirkhill (93.5%) and Kings Park (94.1%).
Period by period
Operators calling here
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| ScotRail | 24,244 | 94.3% | 1.4% |
Operators with their own page for this station are linked to it.
Late train at Croftfoot? Delay Repay
These operators call at Croftfoot and publish Delay Repay rules.
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 1,948 | 96.0% | 0.3% |
| Period 6 of 2026-27 | 1,948 | 96.6% | 0.5% |
| Period 5 of 2026-27 | 1,694 | 96.2% | 0.8% |
| Period 4 of 2026-27 | 1,948 | 94.2% | 1.5% |
| Period 3 of 2026-27 | 1,948 | 93.0% | 4.1% |
| Period 2 of 2026-27 | 1,940 | 93.6% | 1.1% |
| Period 1 of 2026-27 | 2,232 | 94.9% | 1.1% |
| Period 13 of 2025-26 | 1,033 | 94.7% | 2.7% |
| Period 12 of 2025-26 | 1,948 | 94.9% | 0.6% |
| Period 11 of 2025-26 | 1,948 | 96.2% | 0.8% |
| Period 10 of 2025-26 | 1,758 | 93.3% | 1.1% |
| Period 9 of 2025-26 | 1,951 | 89.9% | 3.8% |
| Period 8 of 2025-26 | 1,948 | 92.9% | 0.4% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Similar stations in Scotland
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Burnside (South Lanarkshire) | 24,244 | 94.0% | 1.7% |
| Kirkhill | 24,244 | 93.5% | 2.0% |
| Kings Park | 24,243 | 94.1% | 1.4% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out