GTR at Bellingham
How this operator is doing here
GTR had 33,130 scheduled stops at Bellingham in the 13 periods to Period 7 of 2026-27, 96% of the station's total. 89.4% of recorded arrivals came within three minutes and 4.0% of stops were cancelled.
GTR trains at Bellingham also serve Beckenham Hill (0.9 km south, 90.6% on time, 4.1% cancelled), Catford (1.4 km north, 90.8% on time, 4.1% cancelled), Ravensbourne (2.2 km south, 91.3% on time, 4.0% cancelled), Forest Hill (2.4 km west, 91.7% on time, 3.8% cancelled), Beckenham Junction (2.5 km south, 98.1% on time, 3.1% cancelled) and Sydenham (London) (2.5 km west, 91.9% on time, 3.7% cancelled), which are the stations on its network closest to Bellingham.
Within 30 km of here, GTR runs best at Beckenham Junction, 2.5 km south (98.1%), and worst at Kenley, 13.3 km south-west (66.9%).
The busiest GTR station within 30 km of Bellingham is East Croydon, 8.2 km south-west, with about 813 scheduled stops a day.
Of the 2 operators with enough records at Bellingham, GTR is the most punctual, at 89.4%.
For GTR, Bellingham is the 71st best of 307 ranked stations. Its 89.4% here is 6.5 percentage points above the 82.9% across the whole network.
Cancellations of GTR at Bellingham are near its usual level: 4.0% of scheduled stops, against 4.7% across its network and 4.0% for every operator at the station.
Period by period
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 2,561 | 86.7% | 2.6% |
| Period 6 of 2026-27 | 2,568 | 86.0% | 4.6% |
| Period 5 of 2026-27 | 2,624 | 88.7% | 3.8% |
| Period 4 of 2026-27 | 2,621 | 89.2% | 3.9% |
| Period 3 of 2026-27 | 2,375 | 89.9% | 5.4% |
| Period 2 of 2026-27 | 2,311 | 92.0% | 6.8% |
| Period 1 of 2026-27 | 2,877 | 94.0% | 1.3% |
| Period 13 of 2025-26 | 2,793 | 92.4% | 3.3% |
| Period 12 of 2025-26 | 2,560 | 91.6% | 2.8% |
| Period 11 of 2025-26 | 2,596 | 90.2% | 2.9% |
| Period 10 of 2025-26 | 2,130 | 90.2% | 5.6% |
| Period 9 of 2025-26 | 2,628 | 84.4% | 6.6% |
| Period 8 of 2025-26 | 2,486 | 86.1% | 3.7% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Other operators at Bellingham
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Southeastern | 1,501 | 77.9% | 2.9% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out