St Michaels
STMNorth WestManaged by Merseyrail
How this station is performing
St Michaels has usable figures for 12 of the last 13 four-week periods to Period 7 of 2026-27, covering 43,223 scheduled stops, about 119 a day. In those periods 95.6% of stops arrived within three minutes of the timetable and 1.9% of scheduled stops were cancelled.
St Michaels opened on 1 June 1864 and closed to passengers on 17 April 1972. It reopened on 3 January 1978, 48 years before the latest figures. Among the 5 stations nearest to it with a known opening date, Edge Hill is the oldest (1836) and Brunswick the newest (1998), with St Michaels in between.
The nearest stations to St Michaels are Brunswick (1.7 km north-west), Aigburth (2.2 km south-east), Mossley Hill (2.6 km east), Edge Hill (3.0 km north) and West Allerton (3.2 km east). 45 stations lie within 10 km in all. At 95.6%, St Michaels is more punctual than every one of them; the best of the five, Brunswick, manages 92.5%.
St Michaels is among the most punctual stations in Britain. Its 95.6% puts it 106th out of 2,374 ranked stations, with 105 ahead of it and 2,268 behind, and 11.7 percentage points above the national median of 83.9%.
Compared with 3 stations of a similar size in North West, St Michaels is the most punctual, at 95.6%. The comparison group includes Aigburth (91.8%), Brunswick (92.5%) and Hindley (80.6%).
Period by period
Operators calling here
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Merseyrail | 43,223 | 95.6% | 1.9% |
Operators with their own page for this station are linked to it.
Late train at St Michaels? Delay Repay
These operators call at St Michaels and publish Delay Repay rules.
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 2,514 | 96.8% | 2.1% |
| Period 6 of 2026-27 | 3,357 | 96.6% | 1.6% |
| Period 5 of 2026-27 | 3,358 | – | 1.9% |
| Period 4 of 2026-27 | 3,168 | 94.7% | 1.7% |
| Period 3 of 2026-27 | 3,355 | 96.0% | 2.4% |
| Period 2 of 2026-27 | 3,364 | 96.4% | 0.8% |
| Period 1 of 2026-27 | 3,912 | 96.4% | 3.1% |
| Period 13 of 2025-26 | 3,682 | 97.6% | 2.1% |
| Period 12 of 2025-26 | 3,358 | 96.3% | 1.0% |
| Period 11 of 2025-26 | 3,367 | 95.9% | 2.2% |
| Period 10 of 2025-26 | 3,072 | 95.2% | 1.6% |
| Period 9 of 2025-26 | 3,353 | 93.6% | 2.1% |
| Period 8 of 2025-26 | 3,363 | 91.3% | 2.5% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Similar stations in North West
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out