Llanwrtyd
LNWWalesManaged by TfW Rail
How this station is performing
Llanwrtyd had 3,096 scheduled stops to Period 7 of 2026-27, about 8 a day. 80.8% of recorded arrivals were within three minutes of the timetable and 5.2% of scheduled stops were cancelled.
Llanwrtyd opened on 6 May 1867, 159 years before the latest figures here, and has not been moved since. Of the 5 stations nearest to it with a known opening date, Llanwrtyd is the oldest; the next oldest, Llangammarch, dates from 1867.
The nearest stations to Llanwrtyd are Sugar Loaf (4.4 km south-west), Llangammarch (5.4 km east), Garth (Powys) (7.7 km north-east), Cynghordy (9.9 km south-west) and Cilmeri (13.0 km north-east). 4 stations lie within 10 km in all.
Llanwrtyd is one of 2 stations named after a Village called Llanwrtyd; this one stands 2.4 km from its centre.
Llanwrtyd improved sharply over the past year. In the latest 13 periods 80.8% of stops came within three minutes of the timetable, up 7.4 percentage points from 73.4% in the 13 before. Cancellations rose to 5.2% of scheduled stops from 4.4%, which is 0.8 percentage points more.
Compared with 3 stations of a similar size in Wales, Llanwrtyd is the most punctual, at 80.8%. The comparison group includes Glan Conwy (75.1%), North Llanrwst (80.1%) and Bynea (70.0%).
Period by period
Operators calling here
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Transport for Wales | 3,096 | 80.8% | 5.2% |
Operators with their own page for this station are linked to it.
Late train at Llanwrtyd? Delay Repay
These operators call at Llanwrtyd and publish Delay Repay rules.
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 236 | 82.3% | 2.1% |
| Period 6 of 2026-27 | 258 | 84.5% | 2.3% |
| Period 5 of 2026-27 | 249 | 75.3% | 5.6% |
| Period 4 of 2026-27 | 250 | 74.1% | 13.6% |
| Period 3 of 2026-27 | 256 | 84.6% | 6.3% |
| Period 2 of 2026-27 | 256 | 73.5% | 2.7% |
| Period 1 of 2026-27 | 242 | 83.8% | 5.8% |
| Period 13 of 2025-26 | 278 | 81.5% | 1.1% |
| Period 12 of 2025-26 | 247 | 89.7% | 1.6% |
| Period 11 of 2025-26 | 228 | 82.7% | 8.8% |
| Period 10 of 2025-26 | 201 | 86.0% | 10.9% |
| Period 9 of 2025-26 | 194 | 72.3% | 1.5% |
| Period 8 of 2025-26 | 201 | 78.3% | 6.0% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Similar stations in Wales
| Station | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Glan Conwy | 3,500 | 75.1% | 3.2% |
| North Llanrwst | 3,504 | 80.1% | 3.5% |
| Bynea | 3,646 | 70.0% | 5.0% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out