Skip to content

How punctual is your station? Every stop, every operator, every four weeks.

Castleton Moor

CSMYorkshire and The HumberManaged by Northern Trains

On time, last 13 periods78.6%Great Britain: 83.6%
Cancelled1.3%Great Britain: 3.2%
Stops a day10Scheduled, on average
Punctuality rankNot rankedAmong ranked stations

How this station is performing

Castleton Moor has usable figures for 2 of the last 13 four-week periods to Period 7 of 2026-27, covering 3,775 scheduled stops, about 10 a day. In those periods 78.6% of stops arrived within three minutes of the timetable and 1.3% of scheduled stops were cancelled.

Castleton Moor opened on 1 April 1861, 165 years before the latest figures here, and has not been moved since. Of the 5 stations nearest to it with a known opening date, Castleton Moor is the oldest; the next oldest, Kildale, dates from 1861.

The nearest stations to Castleton Moor are Danby (2.3 km east), Commondale (2.4 km north-west), Lealholm (7.9 km east), Kildale (7.9 km west) and Battersby (9.5 km west). 5 stations lie within 10 km in all. Of the five, Lealholm is the most punctual at 83.4% and Danby the least at 77.9%, with Castleton Moor on 78.6%.

Castleton Moor is named after Castleton, a Village, but the station stands 0.6 km from its centre.

Across the whole run of data, the weakest four-week period for Castleton Moor was Period 1 of 2023-24, at 48.1%, some time before the latest year. The strongest was Period 1 of 2024-25, at 88.9%, and the two are 40.8 percentage points apart. Cancellations peaked at 5.7% of scheduled stops in Period 9 of 2023-24, against 1.3% over the latest 13 periods.

Period by period

60%80%2023-242024-252025-262026-27Period 1 of 2023-24: 48.1%Period 2 of 2023-24: 60.7%Period 3 of 2023-24: 62.9%Period 4 of 2023-24: 81.7%Period 6 of 2023-24: 67.9%Period 7 of 2023-24: 77.2%Period 8 of 2023-24: 64.8%Period 9 of 2023-24: 77.2%Period 10 of 2023-24: 82.1%Period 11 of 2023-24: 86.2%Period 12 of 2023-24: 82.8%Period 1 of 2024-25: 88.9%Period 3 of 2024-25: 76.3%Period 6 of 2024-25: 78.3%Period 7 of 2024-25: 80.3%Period 11 of 2024-25: 88.7%Period 12 of 2024-25: 83.9%Period 2 of 2025-26: 79.1%Period 3 of 2025-26: 78.8%Period 8 of 2025-26: 74.7%Period 10 of 2025-26: 83.2%
This pageGreat Britain
0%2%4%6%Period 1 of 2023-24: 2.3%Period 2 of 2023-24: 1.9%Period 3 of 2023-24: 4.1%Period 4 of 2023-24: 0.0%Period 5 of 2023-24: 5.0%Period 6 of 2023-24: 0.8%Period 7 of 2023-24: 4.4%Period 8 of 2023-24: 2.6%Period 9 of 2023-24: 5.7%Period 10 of 2023-24: 0.8%Period 11 of 2023-24: 1.1%Period 12 of 2023-24: 0.8%Period 13 of 2023-24: 0.7%Period 1 of 2024-25: 0.8%Period 2 of 2024-25: 1.1%Period 3 of 2024-25: 2.6%Period 4 of 2024-25: 4.4%Period 5 of 2024-25: 1.8%Period 6 of 2024-25: 4.3%Period 7 of 2024-25: 3.3%Period 8 of 2024-25: 5.1%Period 9 of 2024-25: 3.3%Period 10 of 2024-25: 5.5%Period 11 of 2024-25: 2.6%Period 12 of 2024-25: 2.9%Period 13 of 2024-25: 1.7%Period 1 of 2025-26: 0.4%Period 2 of 2025-26: 1.5%Period 3 of 2025-26: 0.7%Period 4 of 2025-26: 3.3%Period 5 of 2025-26: 1.1%Period 6 of 2025-26: 1.5%Period 7 of 2025-26: 0.7%Period 8 of 2025-26: 1.1%Period 9 of 2025-26: 2.6%Period 10 of 2025-26: 0.8%Period 11 of 2025-26: 0.0%Period 12 of 2025-26: 0.8%Period 13 of 2025-26: 1.2%Period 1 of 2026-27: 0.9%Period 2 of 2026-27: 2.7%Period 3 of 2026-27: 3.7%Period 4 of 2026-27: 0.0%Period 5 of 2026-27: 2.0%Period 6 of 2026-27: 0.7%Period 7 of 2026-27: 0.0%2023-242024-252025-262026-27

Operators calling here

OperatorScheduled stopsWithin 3 minCancelled
Northern3,77578.6%1.3%

Operators with their own page for this station are linked to it.

The last 13 periods

PeriodScheduled stopsWithin 3 minCancelled
Period 7 of 2026-27296–0.0%
Period 6 of 2026-27296–0.7%
Period 5 of 2026-27296–2.0%
Period 4 of 2026-27296–0.0%
Period 3 of 2026-27296–3.7%
Period 2 of 2026-27296–2.7%
Period 1 of 2026-27340–0.9%
Period 13 of 2025-26326–1.2%
Period 12 of 2025-26241–0.8%
Period 11 of 2025-26296–0.0%
Period 10 of 2025-2625283.2%0.8%
Period 9 of 2025-26272–2.6%
Period 8 of 2025-2627274.7%1.1%

Time of year

60%70%80%90%P1: 66.8%1P2: 70.0%2P3: 73.2%345P6: 72.6%6P7: 78.7%7P8: 69.9%89P10: 82.7%10P11: 87.4%11P12: 83.3%1213

Each point averages that period of the railway year over every year in the data. Period 1 starts in April.

On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out