How punctual is your station? Every stop, every operator, every four weeks.

Shirehampton

SHHSouth WestManaged by Great Western Railway

On time, last 13 periods69.3%Great Britain: 83.6%
Cancelled4.0%Great Britain: 3.2%
Stops a day61Scheduled, on average
Punctuality rankNot rankedAmong ranked stations

How this station is performing

Shirehampton has usable figures for 8 of the last 13 four-week periods to Period 7 of 2026-27, covering 22,210 scheduled stops, about 61 a day. In those periods 69.3% of stops arrived within three minutes of the timetable and 4.0% of scheduled stops were cancelled.

Shirehampton opened on 6 March 1865, 161 years before the latest figures here, and has not been moved since. Of the 5 stations nearest to it with a known opening date, Shirehampton is the oldest; the next oldest, Sea Mills, dates from 1865.

The nearest stations to Shirehampton are Portway Park and Ride (0.7 km north-west), Sea Mills (2.1 km east), Avonmouth (2.2 km north-west), St Andrews Road (3.4 km north) and Clifton Down (5.2 km south-east). 19 stations lie within 10 km in all. Of the five, St Andrews Road is the most punctual at 78.6% and Portway Park and Ride the least at 68.7%, with Shirehampton on 69.3%.

Shirehampton takes its name from a suburb called Shirehampton, and the station stands 1.3 km from its centre.

For Shirehampton, the weakest four-week period in the data is a recent one: Period 7 of 2026-27, when only 61.9% of stops arrived within three minutes of the timetable. The strongest was Period 1 of 2026-27, at 77.8%, which is 15.9 percentage points higher. Cancellations peaked at 14.3% of scheduled stops in Period 9 of 2024-25, against 4.0% over the latest 13 periods.

Period by period

60%70%80%90%2023-242024-252025-262026-27Period 13 of 2025-26: 76.5%Period 1 of 2026-27: 77.8%Period 2 of 2026-27: 68.4%Period 3 of 2026-27: 73.6%Period 4 of 2026-27: 64.6%Period 5 of 2026-27: 63.0%Period 6 of 2026-27: 69.2%Period 7 of 2026-27: 61.9%
This pageGreat Britain
0%5%10%15%Period 1 of 2023-24: 2.0%Period 2 of 2023-24: 1.2%Period 3 of 2023-24: 4.8%Period 4 of 2023-24: 2.6%Period 5 of 2023-24: 3.1%Period 6 of 2023-24: 5.5%Period 7 of 2023-24: 2.9%Period 8 of 2023-24: 4.6%Period 9 of 2023-24: 6.3%Period 10 of 2023-24: 5.8%Period 11 of 2023-24: 3.5%Period 12 of 2023-24: 5.5%Period 13 of 2023-24: 4.4%Period 1 of 2024-25: 6.7%Period 2 of 2024-25: 5.5%Period 3 of 2024-25: 4.9%Period 4 of 2024-25: 7.9%Period 5 of 2024-25: 8.3%Period 6 of 2024-25: 6.1%Period 7 of 2024-25: 7.7%Period 8 of 2024-25: 7.2%Period 9 of 2024-25: 14.3%Period 10 of 2024-25: 7.4%Period 11 of 2024-25: 2.0%Period 12 of 2024-25: 3.9%Period 13 of 2024-25: 2.9%Period 1 of 2025-26: 5.1%Period 2 of 2025-26: 3.3%Period 3 of 2025-26: 3.4%Period 4 of 2025-26: 7.5%Period 5 of 2025-26: 6.4%Period 6 of 2025-26: 3.4%Period 7 of 2025-26: 4.5%Period 8 of 2025-26: 1.8%Period 9 of 2025-26: 3.5%Period 10 of 2025-26: 6.1%Period 11 of 2025-26: 2.2%Period 12 of 2025-26: 1.6%Period 13 of 2025-26: 2.5%Period 1 of 2026-27: 1.3%Period 2 of 2026-27: 4.1%Period 3 of 2026-27: 7.5%Period 4 of 2026-27: 9.9%Period 5 of 2026-27: 7.0%Period 6 of 2026-27: 2.6%Period 7 of 2026-27: 2.8%2023-242024-252025-262026-27

Operators calling here

OperatorScheduled stopsWithin 3 minCancelled
Great Western Railway22,21069.3%4.0%

Operators with their own page for this station are linked to it.

Late train at Shirehampton? Delay Repay

These operators call at Shirehampton and publish Delay Repay rules.

The last 13 periods

PeriodScheduled stopsWithin 3 minCancelled
Period 7 of 2026-271,75261.9%2.8%
Period 6 of 2026-271,45269.2%2.6%
Period 5 of 2026-271,34263.0%7.0%
Period 4 of 2026-271,75264.6%9.9%
Period 3 of 2026-271,63273.6%7.5%
Period 2 of 2026-271,74668.4%4.1%
Period 1 of 2026-272,02677.8%1.3%
Period 13 of 2025-261,91676.5%2.5%
Period 12 of 2025-261,752–1.6%
Period 11 of 2025-261,752–2.2%
Period 10 of 2025-261,584–6.1%
Period 9 of 2025-261,752–3.5%
Period 8 of 2025-261,752–1.8%

On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out