East Midlands Railway at Dronfield
All trains at DronfieldEast Midlands Railway across BritainEast Midlands
How this operator is doing here
East Midlands Railway had 2,337 scheduled stops at Dronfield in the 13 periods to Period 7 of 2026-27, 16% of the station's total. 65.2% of recorded arrivals came within three minutes and 3.2% of stops were cancelled.
East Midlands Railway trains at Dronfield also serve Dore and Totley (4.2 km north-west, 45.9% on time, 3.8% cancelled), Chesterfield (7.7 km south-east, 61.3% on time, 4.3% cancelled), Sheffield (8.6 km north, 57.7% on time, 5.4% cancelled), Grindleford (10.5 km west, 63.8% on time, 3.3% cancelled), Hathersage (12.5 km west, 58.6% on time, 3.3% cancelled) and Bamford (15.2 km west, – on time, – cancelled), which are the stations on its network closest to Dronfield.
Within 30 km of here, East Midlands Railway runs best at Matlock Bath, 20.7 km south (88.1%), and worst at Sheffield, 8.6 km north (57.7%).
The busiest East Midlands Railway station within 30 km of Dronfield is Chesterfield, 7.7 km south-east, with about 97 scheduled stops a day.
East Midlands Railway at Dronfield has slipped a little, from 70.0% within three minutes in the previous 13 periods to 65.2% in the latest 13, a fall of 4.8 percentage points. Cancellations held steady at 3.2% of scheduled stops, against 3.0% before.
Period by period
See how East Midlands Railway Delay Repay works
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 180 | 61.8% | 1.1% |
| Period 6 of 2026-27 | 180 | 58.5% | 2.2% |
| Period 5 of 2026-27 | 168 | 60.5% | 6.0% |
| Period 4 of 2026-27 | 165 | 58.2% | 3.6% |
| Period 3 of 2026-27 | 180 | 59.5% | 9.4% |
| Period 2 of 2026-27 | 180 | 64.3% | 5.0% |
| Period 1 of 2026-27 | 208 | 73.5% | 1.9% |
| Period 13 of 2025-26 | 187 | 62.8% | 2.1% |
| Period 12 of 2025-26 | 186 | 72.0% | 1.6% |
| Period 11 of 2025-26 | 177 | 74.0% | 2.3% |
| Period 10 of 2025-26 | 166 | 70.8% | 2.4% |
| Period 9 of 2025-26 | 180 | 65.5% | 3.3% |
| Period 8 of 2025-26 | 180 | 63.7% | 0.6% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Other operators at Dronfield
| Operator | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Northern | 12,529 | 77.1% | 1.7% |
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out