How this route is doing
Central is a Network Rail route in the North West & Central region. In the 13 four-week periods to Period 7 of 2026-27 it handled 4,927,223 scheduled station stops, and 81.7% of recorded arrivals came within three minutes of the timetable while 3.2% of scheduled stops were cancelled.
Central ranks 10th of 18 routes on 81.7% within three minutes, 1.9 percentage points below the national figure of 83.6%.
Cancellations on Central run lower than the national picture: 3.2% of scheduled stops against 3.2% for Great Britain, 0.0 percentage points fewer. That ranks 9th of 18 routes from the fewest.
Central has slipped a little, from 84.0% within three minutes in the previous 13 periods to 81.7% in the latest 13, a fall of 2.3 percentage points. Cancellations held steady at 3.2% of scheduled stops, against 3.1% before.
Over three full railway years Central has improved each time, from 82.3% within three minutes in 2023-24 to 83.3% in 2024-25 and 83.9% in 2025-26.
Central is the most punctual route in North West & Central, on 81.7%. The other routes in the region are North West (81.0%) and West Coast South (79.1%).
The National Rail timetable for 26 November 2026 schedules 13,207 passenger calls at the stations grouped under Central, an average of 100 for each of the 131 that had a train. The busiest were Birmingham New Street (1,009 calls), Wolverhampton (353 calls), Stourbridge Junction (347 calls) and Birmingham International (306 calls).
On Central the busiest hour of that day began at 08:00, with 789 calls, 60 of them at Birmingham New Street. The first scheduled call of the service day is at Shrewsbury at 04:30 on a Transport for Wales train, and the last is at Wolverhampton at 02:31 on a Avanti West Coast train.
LNR & WMR (80%), Chiltern Railways (6%) and CrossCountry (5%) ran the most trains on Central, from 7 operators calling in all. The most frequent journey touching the route was Stourbridge Town to Stourbridge Junction, with 107 LNR & WMR trains.
Among the busiest stations, the longest wait between 06:00 and midnight was 27 minutes at Coventry, between the 23:00 and the 23:27. Bucknell (11 calls), Hopton Heath (11 calls) and Broome (11 calls) had the fewest trains of any station grouped under Central.
Of the 126 stations here with at least 1,500 scheduled stops in the ORR figures, Stourbridge Town was the most punctual at 100.0% within three minutes and Moreton-in-Marsh the least at 56.4%. Trains calling on Central most often carry on to stations on Western (458 trains) and West Coast South (407 trains).
Period by period
The last 13 periods
| Period | Scheduled stops | Within 3 min | Cancelled |
|---|---|---|---|
| Period 7 of 2026-27 | 386,089 | 79.3% | 2.5% |
| Period 6 of 2026-27 | 385,172 | 79.3% | 2.9% |
| Period 5 of 2026-27 | 360,776 | 79.3% | 4.2% |
| Period 4 of 2026-27 | 362,923 | 76.8% | 4.7% |
| Period 3 of 2026-27 | 357,417 | 81.5% | 3.0% |
| Period 2 of 2026-27 | 364,321 | 82.0% | 3.9% |
| Period 1 of 2026-27 | 440,865 | 85.4% | 2.2% |
| Period 13 of 2025-26 | 415,345 | 86.3% | 2.8% |
| Period 12 of 2025-26 | 380,828 | 87.3% | 1.7% |
| Period 11 of 2025-26 | 372,911 | 86.4% | 4.3% |
| Period 10 of 2025-26 | 342,626 | 82.8% | 2.9% |
| Period 9 of 2025-26 | 380,836 | 75.9% | 3.8% |
| Period 8 of 2025-26 | 377,114 | 79.0% | 2.9% |
Time of year
Each point averages that period of the railway year over every year in the data. Period 1 starts in April.
Other routes in North West & Central
| Route | Within 3 min | Cancelled |
|---|---|---|
| North West | 81.0% | 2.9% |
| West Coast South | 79.1% | 4.6% |
Route figures cover every operator calling at stations on the route and come from a separate table in the same ORR release. The ORR publishes no list of stations by route, so each station is grouped with the nearest of a set of reference stations on each route, or by country for Scotland and Wales; stations near a boundary can fall on the neighbouring route.
On time here means a recorded stop occurred within three minutes of the timetable. Cancelled means a scheduled stop that did not occur. Source: Office of Rail and Road table 3130, Network Rail operational data, in four-week periods. How the figures are worked out